VA Burns Through $408 Million On Sluggish Solar Panel Projects
A lot can be done with four years and eight million dollars — except putting solar panels on a Veterans Affairs parking garage, apparently. The project began in 2012 at the John L. McClellan Memorial Veterans Hospital in Little Rock, Ark., and isn’t expected to be finished until early 2017.
But the lagging construction at the Little Rock medical center turned out to be the tip of the iceberg.
An investigation by the VA inspector general, which was prompted by Arkansas Sen. John Boozman and Rep. French Hill, found that the VA has spent $408 million on solar panel projects in the past six years — all while veterans faced prolonged wait times to see health-care providers and process claims from the scandal-ridden health-care system.
The move to solar is part of the VA’s Green Management Program, which is tasked with installing renewable energy sources at various medical facilities. The probe included 11 out of 15 solar panel projects awarded from 2010 through 2013, which were still incomplete by 2015.
Each of the 11 solar panel sites examined were estimated to be finished within 210 to 372 days from their start date, but on average it took 1,269 for those that were completed.
!~))!
VA Burns Through $408 Million On Sluggish Solar Panel Projects
A lot can be done with four years and eight million dollars — except putting solar panels on a Veterans Affairs parking garage, apparently. The project began in 2012 at the John L. McClellan Memorial Veterans Hospital in Little Rock, Ark., and isn’t expected to be finished until early 2017.
But the lagging construction at the Little Rock medical center turned out to be the tip of the iceberg.
An investigation by the VA inspector general, which was prompted by Arkansas Sen. John Boozman and Rep. French Hill, found that the VA has spent $408 million on solar panel projects in the past six years — all while veterans faced prolonged wait times to see health-care providers and process claims from the scandal-ridden health-care system.
The move to solar is part of the VA’s Green Management Program, which is tasked with installing renewable energy sources at various medical facilities. The probe included 11 out of 15 solar panel projects awarded from 2010 through 2013, which were still incomplete by 2015.
Each of the 11 solar panel sites examined were estimated to be finished within 210 to 372 days from their start date, but on average it took 1,269 for those that were completed.
!~))!